DWSRF Process Overview (Slide 15)

Bidding and Construction • SRF front-end specifications must be included in the plans and

specifications submitted as part of the construction permit application. SRF recommends simply inserting the Exhibit 7A: SRF Required Front-End Specifications (available in PDF or Word format) for ease of review by the DNR project manager. • Currently SRF wastewater and sewer project requirements include Davis- Bacon prevailing wages. Contact Tracy Scebold or Alyson Fleming. • Exhibit 12A includes several forms that must be filled out by the bidders and returned with the bids. Applicants should pay close attention to the Disadvantaged Business Enterprise requirements and forms. • When the applicant identifies the lowest responsive bidder, a packet of bid documents must be submitted to SRF staff for review of eligible costs and concurrence with the bid award. The packet materials are identified in Exhibit 9. • Award concurrence will not be issued until the construction permit is issued and the environmental review is completed.